ES-2350 SubZero
CASE HISTORY:
- This project was a new construction facility of approximately 100,000 sq. feet.
- Application temperature at the time of product installation was –20° F.
- The contractor specializes in the construction of cold storage facilities as well as the installation of polyurea sealant and coating systems.
|
Elastomer Specialties, Inc. Polymers Division Installation Bulletin Three Man Crew Installing ES-2350 Sub-Zero Polyurea
|
BACKGROUND:
- Contractor contacted Elastomer Specialties, Inc. regarding their ES-2350 SUB-ZERO Polyurea joint sealant.
- The contractor needed and was unable to find a heated delivery system. Elastomer Specialties maintains a Subzero rental unit at all times and was able to assist the contractor by providing both the polyurea joint fill material and the equipment for installation.
- The project size was approximately 15,000 linear feet of new construction joints
- Installation temperature was below 0° F.
MATERIAL:
- Material specified: ES-2350 SubZero a hybrid, 1:1 ratio polyurea specifically developed for concrete crack and control joint sealing on indoor, cold storage, warehouse facilities.
- Material, cures in approximately one hour from time of installation and develops a shore A hardness of 92-95.
- While the product can be hand mixed, on all large projects manufacture recommends that the material be installed using a heated, plural component pump system such as the “Condor” Sub-Zero, manufactured by Elastomer Specialties, Inc.
|
INSTALLATION:
- This project located in Enid, Oklahoma was completed in the fall of 2002, and took approximately 3-4 weeks to complete.
- The contractor, Gleason Contractors out of North Dakota was responsible for the new facility construction as well as the joint filling.
- Installation procedure was the same as all new construction joint sealing.
- First the joints were re-saw cut to clean out all dirt, concrete dust and debris.
- The joints were vacuumed prior to installing the ES-2350 Sub-Zero polyurea joint fill.
- Material was installed full depth of the joint.
- Once installed, material was sliced off flush with the concrete surface so as to provide a smooth joint transition for the forklift traffic.
|