ES-9500
CASE HISTORY:
- This new warehouse facility, located around the Tulsa, Oklahoma area, was approximately 3 months old prior to the installation of ES-9500 ElastoKast 95 polyurea.
- Building was 10,000 sq. feet and the owner desired a tough, yet flexible floor coating that could handle heavy forklift traffic.
- Building was set up to be a storage area.
|
Elastomer Specialties, Inc. Polymers Division Installation Bulletin Picture of completed ES-9500 installation
|
BACKGROUND:
- The owner had previously used an epoxy floor coating and was having problems with the coating chipping when heavy steel objects were dropped.
- The idea was that by using an elastomeric coating the chipping problem could be eliminated.
- The owner also needed to have access to the facility as soon as possible.
- The building was a standard metal frame constructed over a concrete slab, saw cut joints every 15 feet.
MATERIAL:
- Product specified: ES-9500 ElastoKast 95. A hybrid polyurea, low pressure spray elastomer.
- Gel time of approximately 3-5 minutes.
- Product develops a hardness of 95 shore A.
- ES-9500 is an aromatic, not considered to be color stable. Owner wanted dark gray and was not concerned about minimal color change.
- The material is a 1:2 ratio and requires a low pressure, plural component pump in order to be mixed and sprayed.
- Equipment: “CONDOR” Deluxe Plural Component Pump, manufactured by ESI.
|
INSTALLATION:
- Prior to installation, the entire floor was shot blasted to obtain the recommended profile.
- Once surface preparation was completed and control joints were filled and properly trimmed, the contractor, Golden Floor Preparation of Golden, Colorado installed IsoPrime using 18 inch medium nap rollers.
- IsoPrime primer was allowed to cure approximately 2-3 hours.
- The product was installed using a two-pass system.
- The first pass contained both the base and intermediate coats, applied at a dry film thickness of 70 mils.
- Because of the rapid cure time and development of high early green strength, a 20 foot x 20 foot section was coated. The operator then returned and immediately applied a 20 mil stipple coat for non-skid purposes.
- The entire project took approximately 5-8 hours to complete.
- Equipment: “CONDOR” Deluxe Plural Component Pump capable of delivering a 1:2 ratio material.
- Material was applied unheated.
- Ambient installation temperature was approximately 60° F.
- Once application was complete, all equipment and masking was removed and the floor was immediately opened to traffic.
|